A defect notice is not something you want to open on a weekend. A Carnegie homeowner rang us on Saturday 3 October after receiving one from the network provider, and we sent an electrician out that afternoon as an emergency call.
What the notice was pointing at
Our electrician started with diagnostic testing at the switchboard: insulation resistance and voltage tests to see what condition the wiring was in. The problem was easy to see. Power came into the house through old cotton insulated mains cable, ending in a ceramic fuse box at the point of attachment, where the overhead supply meets the house. Cotton insulation was standard in Melbourne homes a long time ago. After decades of heat and weather it dries out and breaks down, and that is exactly the kind of thing that gets a home written up.
Replacing the mains on its own would have left the old meter panel and sub board behind it. So we recommended doing the whole path in one go: new mains, a new meter panel, a new sub board with a safety switch on every circuit, and a new earth rod.
We quoted the work on the spot, the owner accepted, and we booked the job for first thing Monday.

Monday: rebuilding the supply
The crew started at 7.30am. The job was a full poly phase (three phase) upgrade, and in order we:
- Disconnected and removed the old cotton mains cable and the ceramic fuse box at the point of attachment
- Fitted a new three phase mains fuse box at the point of attachment
- Ran new 16mm SDI cable from the point of attachment, through the roof space and down the cavity wall, to the meter at the front door and the switchboard behind it
- Fitted a new three phase meter panel and neutral links
- Removed the old sub board enclosure and fitted a new 18 pole enclosure, mounted no higher than 2 metres as current standards require
- Fitted an individual safety switch (RCBO) to every final sub circuit, with an up to date circuit breaker as the main switch, as AS/NZS 3000 requires
- Fitted a new junction filler and extended every existing final sub circuit from the old board into the new one
- Drove a new earth rod on the side of the house and ran 6mm earth cable back to the switchboard

Signed off the same day
Mains work has to be checked by a licensed electrical inspector before it can be livened. We organised a same day fault and emergency inspection, so the inspector came out on the Monday, certified the work and issued the prescribed certificate of compliance. The owner did not have to wait a week for an inspection slot, and the crew packed up mid afternoon with the house running on the new supply.
The old period and interwar homes in the streets behind Koornang Road are where we see this most. Plenty of them have had new kitchens and bathrooms, but the cable coming in from the street is often the original.

Tip for Carnegie homeowners
Have a look where the power line meets your house. If you can see a ceramic fuse box or cracked, fraying cable at that point, get it checked before it turns into a notice or a fault. If you have already received a defect notice, read the date on it and book an electrician early. The fix often involves an inspector, and leaving it to the last week leaves no slack.
Need help in Carnegie?
We work across Carnegie every week from our Box Hill base, and our workmanship carries a lifetime warranty. Find out more about our electricians in Carnegie, or read how we handle switchboard upgrades and repairs.
Got a defect notice or an old fuse box? Call 03 6358 2028 or request a quote. First time with us? Your first service is 15% off, and pensioners and seniors always get 10% off. We are rated 4.9 stars from 188 reviews.